Christmas bypass works less disruptive this year

bypassrailarticle

Over the next few weeks preparation works to the railway signal and telecoms cables will be undertaken and the new rail bridge will be delivered to the site and fabricated within the compound using a 1000 tonne crane. This is due to be completed by early December.

The main installation works will be take place between 11pm on 23rd December and 5am on 28th December. During this time works will take place 24 hours per day with the structure being driven in to place during the morning of the 26th December.

A spokesman from Network Rail confirmed “ It is expected these activities will produce some noise and disruption. Efforts will be made to minimise the noise as much as possible and will not be as disruptive as the piling works carried out over Christmas 2008.”

Sarah McArdie, Community Relations Manager, from Network Rail, added “I would like to apologise for any inconvenience that our works may cause you but we are sure you can appreciate the long-term benefits that the work will bring to the travelling public in terms of a more reliable and improved road and rail network.”

If you have any queries in respect to the work, Network Rail can be contacted via their 24 hour national helpline on 08457 114 141.

Tags:
A34 Bypass, Birse, Network Rail
Advertisement
Advertisement
Advertisement
Advertisement

Comments

Here's what readers have had to say so far. Why not add your thoughts below.

Marc Asquith
Thursday 3rd December 2009 at 5:23 pm
I have to say that "less disruptive" is a substantial understatement. Last year the piling works in Nether Alderley, which started at un-godly hours and went on all day through the entire christmas period, could be heard in south Wilmslow. This year it will only be the local residents in Nether Alderley that are likely to be disturbed. While I am writing, can I just express my admiration for the people of Birse Rail. They have a 100 hour slot in which to completely take up the West Coast Main Line, put in a bridge and then return the line to perfect working order. The penalty clauses for failing to make the deadline are draconian and they successfully carry out this type of work year in year out. Hat's off to Birse Rail.