Temporary traffic lights will be installed on the A535 Chelford Road tomorrow to complete the works to both raise and strengthen the parapets on the existing culvert, immediately east of the new bypass.
Doug Mackie, Project Manager, said "These works are anticipated to take a week. This work originally started on October 4th, we completed the south side but then resources were needed more urgently elsewhere on the scheme.
"Works to Bollington Lane and the junctions with A34 & A537 are now substantially complete, which enables us to re-commence at Monks Heath, where for the remaining works we need to occupy part of the A34, which requires one lane of traffic to be diverted."
From October 25th northbound traffic on the A34, and any traffic on the A537 which wishes to turn right on to the A34, will be diverted along the A537 and right up Bollington Lane. The new permanent traffic signals will be operational to control traffic turning right at the A537/ Bollington Lane junction, and it will be necessary for both these signals and those at Monks Heath to be manually controlled at peak periods.
South bound A34 traffic will travel through Monks Heath as normal but will be moved onto the north bound carriageway when required by the operations.
Doug Mackie added "This arrangement will be in place till works are complete, currently anticipated to be immediately before Christmas. We appreciate that this will inevitably cause some disruption and we will do our best to minimize the impact."
Click here to view a map of the diversion route.





