The A34 bypass will be closed for overnight from 7pm until 6pm from tomorrow ( Friday, 18 March) for 4 nights to enable Cheshire East Highways to carrying out works.
The works will take place in four phases as detailed below - Please note Phase 4 is scheduled to take place the day before Phase 3 (?).
Phase 1 – Birrell Way and Pendleton Way 18/03/22
- Retexturing works to improve skid resistance
- Road markings renewal – centre line, roundabouts and approaches
- 4 Vehicle restraint repairs
- Gully cleansing
- CAT 1 defect repairs
- Street lighting repairs
- Ecology Surveys to enable vegetation cut back
- Vegetation cut back to signage
- Sign Cleaning
- Carriageway sweeping
Phase 2 – Birrell Way and MacLean Way 19/03/22
- Retexturing works to improve skid resistance
- Road markings renewal – centre line, roundabouts and approaches
- 4 Vehicle restraint repairs
- CAT 1 Repairs
- Street lighting repairs
- Vegetation cut back to signage
- Sign Cleaning
- Carriageway sweeping
Phase 4 – Ainslie Way 20/03/22
- Retexturing works to improve skid resistance
- Road markings renewal – centre line, roundabouts and approaches
- 6 Vehicle restraint repairs
- Gully cleansing
- CAT 1 Repairs
- Street lighting repairs
- Ecology Surveys to enable vegetation cut back
- Vegetation cut back
- Sign Cleaning
- Carriageway sweeping
Phase 3 – MacLean Way and Ainslie Way 21/03/22
- Retexturing works to improve skid resistance
- Road markings renewal – centre line, roundabouts and approaches
- 4 Vehicle restraint repairs
- Gully cleansing
- CAT 1 Repairs
- Street lighting repairs
- Ecology Surveys to enable vegetation cut back
- Vegetation cut back
- Sign Cleaning
- Carriageway sweeping
Access for Handforth Dean retail park will be via Stanley Green and access for Total Fitness park will be via Hall Moss Lane. Signed diversions will also be in place during the works.